HOW TO CALCULATE CRITICAL PATH, FREE FLOAT AND TOTAL FLOAT ?

Contributed By:
Critical Path Method

Activity
Predecessors
Three time Estimates


a
m
b
A
---

2

B
A

5

C
A

10

D
A

6

E
B,C,D

9

F
E

4

G
F

3


here we have not putted the values of a and b as it is not required in calculating the critical path, free float and total float.

Step-1: Draw Network Diagram




Step-2: Find Critical Path


P1: A > B > E > F > G = 23
P2: A > C > E > F > G = 28 -> Highest time = critical path
P3: A > D > E > F > G = 24

Step-3: Calculate Early start, late start, early finish and late finish.

SHOWN IN THE DIAGRAM.

Step-4: Calculate Total float and free float.


TOTAL FLOAT=LATE START - EARLY START



Total Float (TF)                                                                   

A
0-0=0
 B
7-2=5
C
2-2=0
D
6-2=4
E
12-12=0
F
21-21=0
G
25-25=0












FREE FLOAT OF A ACTIVITY= EARLY START OF NEXT ACTIVITY - EARLY FINISH OF CURRENT ACTIVITY

Free float (ff)
A
2-2=0
B
12-7=5
C
12-12=0
D
12-8=4
E
21-21=0
F
25-25=0