Critical Path Method
Activity | Predecessors | Three time Estimates | ||
| | a | m | b |
A | --- | | 2 | |
B | A | | 5 | |
C | A | | 10 | |
D | A | | 6 | |
E | B,C,D | | 9 | |
F | E | | 4 | |
G | F | | 3 | |
Step-1: Draw Network Diagram
Step-2: Find Critical Path
P1: A > B > E > F > G = 23
P2: A > C > E > F > G = 28 -> Highest time = critical path
P3: A > D > E > F > G = 24
Step-3: Calculate Early start, late start, early finish and late finish.
SHOWN IN THE DIAGRAM.
Step-4: Calculate Total float and free float.
TOTAL FLOAT=LATE START - EARLY START
Total Float (TF)
A | 0-0=0 |
B | 7-2=5 |
C | 2-2=0 |
D | 6-2=4 |
E | 12-12=0 |
F | 21-21=0 |
G | 25-25=0 |
|
Free float (ff)
A | 2-2=0 |
B | 12-7=5 |
C | 12-12=0 |
D | 12-8=4 |
E | 21-21=0 |
F | 25-25=0 |